Zero Discharge Operation

Zero Discharge Operation

Meeting discharge limits with no liquid waste stream — a design outcome, not an add-on.

Application Scenarios

Zero Discharge Operation

Zero liquid discharge means the plant reuses all of its process water and produces only solid cake. It is achieved by balancing water input, water lost with product and water lost with cake — not by adding a treatment unit at the end.

The critical numbers are the moisture content of every output stream. Product moisture, cake moisture and evaporation together must equal the water entering with the feed coal plus any make-up water.

Dehui designs plants toward this balance from the flow sheet stage: dewatering screens and centrifuges on the product side, thickener and filter press on the slime side, and a water balance calculation that closes on paper before anything is built.

Selection from your coal dataCommissioning support includedSpare parts against original specification
Key Specifications

Zero Discharge Operation — What Decides the Specification

Indicative values. Final figures follow from your coal analysis and site conditions.

ParameterTypical Range
ParameterTypical requirement Water balanceCalculated and closed at design stage
Product moistureControlled by dewatering screen and centrifuge
Cake moistureControlled by filter press type and cycle
Make-up waterOnly what is lost with product and cake
DischargeNone in normal operation
Where We Work

What We Have Learned on Site

Zero discharge is a mass balance outcome. If the numbers do not close at design stage, no amount of equipment will fix it later.

Rain water and floor wash-down are often overlooked inputs. They can break an otherwise closed balance.

Cake moisture is the largest controllable water loss. A few percentage points here changes the make-up water requirement materially.

FAQ

Zero Discharge Operation — Frequently Asked

Is zero discharge realistic for a coal washing plant?

Yes for most plants, because the product and cake can absorb the water that enters with the feed. The design has to be checked against your actual moisture figures.

What is the main risk to a zero discharge design?

Unaccounted water inputs — rain, wash-down, seal water — and slime output exceeding press capacity.